Plan a re-rig · Lesson 11 of 15
Coordinate unstepping and installation
Agree with the yard who controls mast support, lifting equipment, exclusion zones and the release sequence. Trace wiring, antennas, mast boot, partners and furler before the lift. A deck-stepped mast and a keel-stepped mast have different access and handling requirements. Leave loaded stays and mast support to the lift team.
Workshop assignment
Prepare a handover sheet with disconnect points, photographs, labeled storage for fittings, and a named person responsible for sign-off before releasing the crane.
Check your understanding
When should an owner disconnect a loaded stay to save crane time?
Compare your reasoning
Leave it in place. The lift supervisor directs load transfer and release under the approved lifting plan.
Rigging references · Seldén Mast manuals · Sta-Lok terminal instructions