A buyer finds new wire invoices but no chainplate inspection record, a furler that binds and a rust trail inside a locker. Separate verified work from unresolved findings. Prioritize assessment before sailing, collect the underlying specifications, and ask the yard to quote inspection access separately from replacement.
Workshop assignment
Assemble a rig drawing, stay inventory, photo log, open findings, approved work scope and commissioning record. Set the follow-up inspection with the rigger using the boat’s use, history and manufacturer guidance.
Check your understanding
What evidence would close the locker finding?
Compare your reasoning
Identification of the affected attachment, inspection of the metal and supporting structure, documented corrective work if required, and sign-off by the responsible specialist.